Drawings arrive in feet and inches, design codes work in millimetres and megapascals, the batching plant thinks in cubic metres, and the landowner talks in marlas. A civil engineer who cannot move between these systems quickly will make mistakes — usually expensive ones.
This is a complete, verified reference: conversion tables for every quantity you will meet on site, plus worked examples showing how the conversions are actually used.
Length

| From | To | Multiply by |
|---|---|---|
| 1 inch (in) | millimetres | 25.4 |
| 1 foot (ft) | metres | 0.3048 |
| 1 yard (yd) | metres | 0.9144 |
| 1 mile | kilometres | 1.60934 |
| 1 metre (m) | feet | 3.28084 |
| 1 kilometre (km) | miles | 0.62137 |
Key site facts: 1 m = 1000 mm = 100 cm; 1 ft = 12 in; 1 yd = 3 ft.
Area (Including Pakistani Land Units)
| From | To | Multiply by |
|---|---|---|
| 1 ft² | m² | 0.092903 |
| 1 yd² | m² | 0.836127 |
| 1 m² | ft² | 10.7639 |
| 1 acre | m² | 4046.86 |
| 1 acre | ft² | 43,560 |
| 1 hectare | m² | 10,000 |
| 1 hectare | acres | 2.47105 |
Pakistani land units (Punjab standard):
| Unit | Equals |
|---|---|
| 1 marla | 272.25 ft² = 25.29 m² |
| 1 kanal | 20 marla = 5,445 ft² = 505.86 m² |
| 1 acre | 160 marla = 8 kanal = 43,560 ft² |
| 1 murabba | 25 acres |
Worked example: A plot is 2 kanal. In square metres: 2 × 505.86 = 1,011.7 m². In marlas: 2 × 20 = 40 marla.
For Pakistani land units like marla and kanal, use our Land Area Converter to convert any plot size instantly.
Volume
| From | To | Multiply by |
|---|---|---|
| 1 ft³ | m³ | 0.0283168 |
| 1 m³ | ft³ | 35.3147 |
| 1 yd³ | m³ | 0.764555 |
| 1 litre (L) | m³ | 0.001 |
| 1 litre | ft³ | 0.0353147 |
| 1 US gallon | litres | 3.78541 |
| 1 imperial gallon | litres | 4.54609 |
| 1 m³ | litres | 1,000 |
Key site facts: 1 m³ = 1000 L; a standard concrete mixer truck carries 6–8 m³. Discharge is also volume per time: 1 cusec (ft³/s) = 0.02832 m³/s.
Worked example: A footing needs 4.5 m³ of concrete. In cubic feet: 4.5 × 35.3147 = 158.9 ft³. In litres: 4.5 × 1000 = 4,500 L.
Mass
| From | To | Multiply by |
|---|---|---|
| 1 pound (lb) | kg | 0.453592 |
| 1 kg | lb | 2.20462 |
| 1 metric tonne | kg | 1,000 |
| 1 metric tonne | lb | 2,204.62 |
| 1 US (short) ton | kg | 907.185 |
| 1 maund (trade) | kg | 40 (Pakistan’s standard trade maund; the historical British imperial maund was 37.32 kg) |
Worked example: 1 m³ of normal concrete weighs about 2,400 kg = 2.4 tonnes = 2.4 × 2204.62 = 5,291 lb. This single number drives truck counts, crane picks, and dead-load estimates.
Rebar Weight (Used Daily on Site)
The weight of steel bars per metre follows one simple formula:
Weight (kg/m) = D² / 162, where D = bar diameter in mm
| Bar diameter | Weight per metre |
|---|---|
| 10 mm | 0.617 kg/m |
| 12 mm | 0.888 kg/m |
| 16 mm | 1.579 kg/m |
| 20 mm | 2.466 kg/m |
| 25 mm | 3.853 kg/m |
| 32 mm | 6.313 kg/m |
Worked example: A bar bending schedule calls for 85 m of 20 mm bars. Weight = 85 × 2.466 = 209.6 kg. The 162 in the denominator comes from the density of steel (7,850 kg/m³): it is exact enough for every site calculation. For lap length calculations using these bars, see the lap length guide.
Steel bar weights for every common diameter are covered by our Steel Bar Weight Calculator.
Force
| From | To | Multiply by |
|---|---|---|
| 1 newton (N) | lbf | 0.224809 |
| 1 kilonewton (kN) | lbf | 224.809 |
| 1 kgf | N | 9.80665 |
| 1 tonne-force | kN | 9.80665 |
| 1 MN | kN | 1,000 |
Key fact: 1 kg of mass weighs 9.81 N on Earth. Site engineers often say “10 tonnes” when they mean a 98.1 kN load — fine for talk, but use proper force units in calculations.
Pressure and Stress (The Most-Used Table in Design)
| From | To | Multiply by |
|---|---|---|
| 1 N/mm² | MPa | 1 (exactly) |
| 1 MPa | psi | 145.038 |
| 1 psi | kPa | 6.89476 |
| 1 kg/cm² | MPa | 0.0980665 |
| 1 kg/cm² | psi | 14.2233 |
| 1 kPa | kN/m² | 1 (exactly) |
| 1 bar | MPa | 0.1 |
| 1 bar | psi | 14.5038 |
Worked example 1: A cylinder test gives 32 N/mm². In MPa: 32 MPa. In psi: 32 × 145.038 = 4,641 psi.
Worked example 2: A US specification calls for 3,000 psi concrete. In MPa: 3000 × 0.00689476 = 20.7 MPa. Careful: a psi figure is cylinder strength, while M-grades are cube strength. 20.7 MPa in cylinders is roughly 25 MPa in cubes — so 3,000 psi concrete is closer to M25 than to M20.
Worked example 3: A soil bearing capacity of 150 kN/m² = 150 kPa = 150 × 0.145038 = 21.8 psi.
Density and Unit Weight
| From | To | Multiply by |
|---|---|---|
| 1 lb/ft³ | kg/m³ | 16.0185 |
| 1 g/cm³ | kg/m³ | 1,000 |
| 1 kg/m³ (mass density) | kN/m³ (unit weight) | ÷ 1,000 × 9.81 |
So concrete at 2,400 kg/m³ has a unit weight of 2,400 × 9.81 / 1,000 = 23.5 kN/m³ (commonly rounded to 24 kN/m³ in design). For the full list of material unit weights, see the unit weight guide.
Speed and Temperature
| From | To | Multiply by |
|---|---|---|
| 1 km/h | m/s | 0.277778 |
| 1 mph | km/h | 1.60934 |
| °C to °F | — | °F = °C × 9/5 + 32 |
| °F to °C | — | °C = (°F − 32) × 5/9 |
Worked example: Concrete temperature limit 35°C = 35 × 9/5 + 32 = 95°F.
Money and Counting (Pakistani Site Practice)
| Unit | Equals |
|---|---|
| 1 lakh | 100,000 |
| 1 crore | 10,000,000 (100 lakh) |
| 1 arab | 1,000,000,000 (100 crore) |
Practical Tips
- Keep mm and m straight. The single most common site arithmetic error is mixing millimetres and metres in one formula — a beam 300 mm wide is 0.3 m, not 300 m.
- Write the units in every calculation. If the units cancel correctly, the number is usually right.
- psi ↔ MPa shortcut: multiply psi by 0.007 for a quick mental MPa (≈ 3,000 psi ≈ 21 MPa).
- The D²/162 rule for rebar weight and the 2,400 kg/m³ concrete figure should be memorised — you will use them weekly.
- Land units vary by province — the marla above is the Punjab standard (272.25 ft²). Confirm the local standard before any transaction.
Common Conversion Mistakes That Cost Money
Most conversion errors on site are not about not knowing the factor — they are about using the right factor in the wrong place. These are the five mistakes I see again and again, and each one has cost somebody real money.
Mixing millimetres and metres in one formula. A beam 300 mm wide is 0.3 m, not 300 m. Put both units into one calculation and a concrete quantity comes out a thousand times too big — and if nobody catches it, the order goes out wrong. Rule: convert everything to one unit before you start calculating, and write the unit next to every number.
Reading psi as MPa. A specification calling for 3,000 psi concrete means about 20.7 MPa cylinder strength — roughly 25 MPa cube strength, about M25 grade. Read it as 30 MPa and you will order a richer, more expensive mix than the design needs. The quick mental check: multiply psi by 0.007 and you get MPa (3,000 × 0.007 ≈ 21 MPa).
US gallon vs imperial gallon. A US gallon is 3.79 litres; an imperial gallon is 4.55 litres — a 20% difference. On water quantities for curing or on imported equipment ratings, that 20% is the difference between enough and not enough. Always check which gallon the document means.
Tonne vs ton. A metric tonne is 1,000 kg. A US (short) ton is 907 kg. On a steel delivery of 50 tons, the difference is more than 4,500 kg — about the weight of a small truck. Confirm the unit on the delivery note before you sign it.
Assuming the marla is the same everywhere. The marla in the tables above is the Punjab standard (272.25 ft²). Other provinces and older records use different values. Before any land transaction, confirm the local standard in writing — a wrong marla has undone more than one deal.
Worked Examples from Real Site Work
Example 1 — concrete for a slab. A slab is 10 m long, 8 m wide and 150 mm (0.15 m) thick. Volume = 10 × 8 × 0.15 = 12 m³. In cubic feet: 12 × 35.3147 = 423.8 ft³. Cement needed (site rule of thumb, about 8 bags of 50 kg per m³ for M20): 12 × 8 = 96 bags. Always add 5% wastage on top — order 100 bags, not 96.
Example 2 — steel weight for a beam. A beam needs 6 bars of 16 mm, each 12 m long. Total length = 6 × 12 = 72 m. Weight = 72 × 1.579 kg/m = 113.7 kg. Add lap length before you finalise the quantity — laps are steel too, and forgetting them is the classic bar bending schedule error.
Example 3 — buying a plot. A plot is advertised as 1 kanal 10 marla. In marlas: 20 + 10 = 30 marla. In square metres: 30 × 25.29 = 758.7 m². In square feet: 30 × 272.25 = 8,167.5 ft². Check all three numbers against the registry papers before paying anything.
How to Check Your Answer Before You Trust It
Every conversion deserves a ten-second sanity check. First, the order-of-magnitude test: 1 m³ of concrete weighs about 2.4 tonnes. If your calculation says a 12 m³ slab weighs 24 tonnes or 240 tonnes, a decimal has slipped — the right answer is about 28.8 tonnes. Second, the units test: write the units through the calculation and make sure they cancel correctly — metres times metres must give square metres, never metres. Third, the second-path test: convert the same quantity a different way and see if the answers agree. Convert 100 ft² to m² by multiplying by 0.0929 (9.29 m²) and by dividing by 10.764 (9.29 m²). Two paths, one answer — then you can trust it.
Frequently Asked Questions
How many marlas are in one acre?
160 marlas (Punjab standard). One acre = 8 kanal = 43,560 ft² = 4,046.86 m².
What is 1 N/mm² in psi?
1 N/mm² = 1 MPa = 145.04 psi.
How much does 1 cubic metre of concrete weigh?
About 2,400 kg, or 2.4 metric tonnes (23.5 kN/m³).
What is the formula for rebar weight per metre?
Weight (kg/m) = D²/162, where D is the bar diameter in millimetres. A 20 mm bar weighs 2.466 kg/m.
How many cubic feet are in 1 brass?
1 brass = 100 ft³ = 2.83 m³. It is the unit sand and aggregate are still sold in on many Pakistani sites.
What is 1 cusec in litres per second?
1 cusec (1 ft³/s) = 28.32 litres per second. It is the standard unit for canal and drain discharges.
How do I convert kg/cm² to MPa quickly?
Multiply by 0.0981 — or, for a site shortcut, divide by 10 (the answer comes out about 2% high, which is fine for a quick check). So 250 kg/cm² ≈ 24.5 MPa.
Final Thoughts
Bookmark this page — unit conversion is one of those skills that quietly underpins every estimate, every test result, and every drawing you read. When a conversion feeds into a structural calculation, double-check it; when it feeds into a purchase order, triple-check it.
Written by Mohsin Raza Adil — BSc Civil Engineering Technologist (NTC-registered), Pakistan.