Cement Calculator — Bags for Concrete & Mortar
1 bag = 50 kg = 1.25 cu ft. Includes 5% wastage.
Save or share — branded with Civil Technologist.
Related Construction Calculators
Need concrete for your project? Try our free Concrete Calculator — estimate concrete volume, cement bags, sand, aggregate, water and material cost for slabs, columns, beams, stairs and footings, with step-by-step working.
How to Use This Cement Calculator
- Select work type — Concrete (slab, beam, column, footing) or Mortar (brickwork, plaster).
- Pick the grade/ratio — M15 (1:2:4), M20 (1:1.5:3), or M25 (1:1:2) for concrete; 1:4 or 1:6 for mortar.
- Enter volume in cubic feet — measure length × width × thickness of your element.
- Set wastage % — 5% is standard; use 7–10% for plaster and brickwork where spillage is higher.
- Press Calculate Cement — the cement calculator shows bags, sand, aggregate, and kg instantly.
Cement Calculation Formula (How the Calculator Works)
This cement calculator uses the dry volume method trusted on sites across Pakistan:
- Step 1: Wet volume (your input) × 1.52 = dry volume.
- Step 2: Cement volume = dry volume × cement parts ÷ total parts. For M20 (1:1.5:3): 1 ÷ 5.5.
- Step 3: Convert to bags — 1 bag = 50 kg = 1.25 cubic feet.
- Step 4: Add your wastage percentage on top.
Example: 100 cft of M20 concrete → dry volume = 152 cft → cement = 152 × (1/5.5) = 27.6 cft → 27.6 ÷ 1.25 = 22 bags (before wastage).
Cement Bags Required per 100 Cft of Concrete
| Grade | Ratio | Cement bags (50 kg) | Sand (cft) | Aggregate (cft) |
|---|---|---|---|---|
| M15 | 1:2:4 | ~17 bags | ~43 | ~87 |
| M20 | 1:1.5:3 | ~22 bags | ~41 | ~83 |
| M25 | 1:1:2 | ~30 bags | ~38 | ~76 |
Cement for Mortar (Brickwork & Plaster)
| Mortar ratio | Use | Cement per 100 cft of mortar |
|---|---|---|
| 1:4 | Rich mortar — plaster, waterproofing | ~21 bags |
| 1:6 | Standard brickwork mortar | ~15 bags |
Worked Example: 10 × 10 ft Slab, 6 inches Thick
- Volume = 10 × 10 × 0.5 = 50 cft, grade M20, 5% wastage.
- Enter 50 in the cement calculator → result: ~12 bags of cement, ~21 cft sand, ~43 cft aggregate.
- On site, order 13 bags — one spare bag is cheaper than a stalled pour.
How Much Wastage Should You Add?
- Concrete (machine mixed): 3–5%
- Hand-mixed concrete: 5–7%
- Brickwork: 7–10% (mortar drops, joints)
- Plaster: 10–12% (rebound and spillage)
Frequently Asked Questions
How many cement bags are in 1 cubic meter of M20 concrete?
About 8 bags per cubic meter by the nominal-mix method — roughly 400 kg of cement per m³. A designed M20 mix uses less, typically around 320–360 kg per m³.
What is the dry volume factor in cement calculation?
1.52 for concrete and 1.33 for mortar. It accounts for the voids between sand and aggregate particles.
How many bags of cement per cubic foot?
One 50 kg bag occupies 1.25 cubic feet. Divide any cement volume in cft by 1.25 to get bags.
Which grade of concrete needs the most cement?
Higher grades need more cement: M25 (1:1:2) needs roughly double the cement of M15 (1:2:4) for the same volume.
Does this cement calculator work for plaster?
Yes — select “Mortar”, choose 1:4 or 1:6, enter the plaster volume (wall area × thickness), and add 10% wastage.
Why does my site always run short of cement?
Three usual reasons: no wastage in the estimate, bulking of moist sand, and spillage during hand mixing.
What is the weight of 1 bag of cement in kg?
Standard bag = 50 kg in Pakistan (1.25 cft by volume).
Can I use this cement calculator for a footing or column?
Yes — any concrete element. Calculate its volume (length × width × depth) in cubic feet and enter it.
Related: Concrete Calculator — full material + cost estimate. Brick Calculator — bricks, cement and sand for any wall.
Written by Mohsin Raza Adil — BSc Civil Engineering Technologist (NTC-registered), Pakistan.
Cement Bags per Cubic Metre of Concrete
Many drawings and BOQs give quantities in cubic metres, not cubic feet. One cubic metre equals 35.31 cft, so the per-100-cft figures above convert as follows (before wastage):
| Concrete Grade | Mix Ratio | Cement Bags per m³ | Cement Bags per 100 cft |
|---|---|---|---|
| M15 | 1 : 2 : 4 | ≈ 6.0 bags | ≈ 17 bags |
| M20 | 1 : 1.5 : 3 | ≈ 7.8 bags | ≈ 22 bags |
| M25 | 1 : 1 : 2 | ≈ 10.6 bags | ≈ 30 bags |
So if a drawing calls for 10 m³ of M20 concrete, you need roughly 78 bags of cement before wastage — about 82 bags with 5% wastage added. The calculator above does this conversion for you automatically when you enter the volume in metres.
Cement Bags for Common RCC Elements
Site engineers rarely order for a full 100 cft at once — they order element by element. These quick figures are worked out from the same mix calculations the calculator uses (M20 grade, before wastage):
| Element | Size / Volume | Cement Needed (M20) |
|---|---|---|
| Roof slab | 100 sq ft area, 5 inches thick (≈ 41.7 cft) | ≈ 9–10 bags |
| Roof slab | 10 × 10 ft, 6 inches thick (50 cft) | ≈ 12 bags (order 13) |
| Column | 9 in × 12 in section, 10 ft high (7.5 cft) | ≈ 2 bags |
| Beam | 9 in × 12 in section, 10 ft long (7.5 cft) | ≈ 2 bags |
| Isolated footing | 4 × 4 ft, 1 ft deep (16 cft) | ≈ 3.5 bags |
For lean concrete under footings and floors (M15 or a 1:4:8 mix), the cement drops sharply — the same 100 cft needs only about 17 bags in M15 and roughly 9–10 bags in a lean 1:4:8 mix. Always confirm the grade on the drawing before ordering; guessing one grade higher on a full house can waste 40–50 bags.
Why the Dry Volume Factor Is 1.52
Fresh concrete shrinks as it settles and the voids between aggregate particles fill with sand and cement paste. To get 100 cft of finished (wet) concrete, you therefore need about 152 cft of dry materials — this is the dry volume factor of 1.52 used in every calculation on this page. For mortar the factor is lower, about 1.33, because mortar has no coarse aggregate. If a supplier or mistri uses a different factor, your bag count will differ — this is the single most common reason two people’s cement estimates for the same slab do not match.
Common Cement Estimation Mistakes on Site
- Forgetting the dry volume factor — calculating bags from the wet volume directly under-orders cement by about one-third, and the pour stops mid-element.
- Using one bag = 1 cft — a 50 kg bag of cement is 1.25 cft (density 1440 kg/m³). Using 1 cft over-orders by 25%.
- Ignoring wastage and spillage — add 5% for careful machine-mixed work and up to 10% for manual mixing and long carrying distances.
- Mixing up concrete and mortar ratios — a 1:6 mortar needs about 15 bags per 100 cft, while M25 concrete needs about 30. Applying the wrong table doubles or halves the order.
- Not deducting openings in plaster and brickwork — doors and windows are deducted from wall quantities in a proper estimate; the calculator’s mortar mode assumes net volume, so deduct large openings from your wall volume first.
More Questions About Cement Bags
How many cement bags are needed for a 100 sq ft slab?
For a 100 sq ft roof slab, 5 inches thick, in M20 concrete: about 9–10 bags of cement (roughly 12 bags if the slab is 6 inches thick). Add one extra bag as a safety margin rather than risking a stopped pour.
How many bags of cement are in 1 cubic metre of concrete?
It depends on the grade: about 6 bags for M15, 7.8 bags for M20 and 10.6 bags for M25, before wastage. These figures use the standard dry volume factor of 1.52 and a 50 kg bag.
Why does my mistri’s estimate differ from the calculator?
Usually because of the dry volume factor (1.52 vs a rough 1.5 or none), the bag volume used (1.25 cft vs 1 cft), or a different wastage allowance. Ask which three numbers he used — if they match the ones on this page, the answers will match too.
Does the brand of cement change the number of bags?
No. All standard OPC bags in Pakistan are 50 kg with the same density used here, so the bag count is the same for every brand. What changes with brand and storage is quality and setting behaviour, not quantity — and cement stored badly loses strength, which no extra bags can fully fix. See our guide on how to store cement on site.